WORK PERFORMED
- Removal of abandoned objects
- Pressure washing silos & elevator
- Repairing spalled concrete
- Application of protective coating
- Additional minor repairs
SUMMARY

TIME
Project completed in about 1 month

COST
Completed during a pre-scheduled outage

SAFETY
Completed without any near misses or safety incidents
CLIENT NEED
Silos and elevator in need of repairs
Removing growth on structure walls
Pressure washing the structures using rope access
ACCESS
Spalling concrete on elevator building
Spalling concrete, exposed rebar on silos
Applying repair mortar
SOLUTION
Coating the structures using rope access
Silo roof coated
Repairs complete
RESULTS