Power Generation
WORK PERFORMED
- Demolition of existing liner
- Washdown of stack interior & exterior
- Patching holes in steel shell interior & exterior
- Replacement of damaged or missing liner anchors
- Installation of new gunite lining system
- Coating stack & doghouse exterior
SUMMARY

TIME
Project completed in 2-3 weeks

COST
Completed during a pre-scheduled outage

SAFETY
Completed without any near misses or safety incidents
CLIENT NEED
Stack in repair
Failing liner
Liner demolition in progress
ACCESS
Liner demolition complete
Holes in stack shell
Installing patches over holes in interior
SOLUTION
Stack ring installed
Installing new steel horn anchors
Patches on exterior
New gunite liner installed
Stack coating complete
Stack coating complete
RESULTS