770-255-1313
24hr Emergency Service
770-255-1313
24hr Emergency Service
Multi-Craft Services
Bulk Material
Mechanical Services
Multi-Craft Services
Bulk Material
Mechanical Services

RECOVERY BOILER STACK INSPECTION

Pulp & Paper

SUMMARY

Industrial Access conducted a condition assessment on two steel single-wall recovery boilers at a paper mill. A comprehensive inspection was performed and, with the client’s approval, additional necessary repairs were made to ensure the safety on site. Based on the inspection findings, Industrial Access developed a thorough recommended maintenance strategy for the facility moving forward.

TIME

2 days for inspection, 5 days for repairs

COST

Completed during a pre-scheduled shutdown

SAFETY

Completed with no safety compromises

CLIENT NEED

A paper mill in the southern United States was scheduled for ASCE Class II exterior and interior inspections for two of their recovery boiler stacks. Both boilers are steel, single-wall, approx. 148’ in height and 8’6” in diameter with platforms and ladders installed. The client contracted Industrial Access (IA) to evaluate the condition of both stacks and identify any areas in need of attention and repair services.

Steel smokestacks are subject to deterioration and the appearance of corrosion more rapidly than any other type of chimney due to the nature of their construction. Because heat, weathering, and acid attack are a constant threat to steel, regular monitoring and maintenance is required to extend the life of a steel chimney.

ACCESS

The inspections were performed using a crane with a man basket to allow IA specialists perform the required tests and assessments. In addition to the existing platforms, scaffolding and other points of access were also used for the exterior inspection. Due to the lack of access space for the crane basket, some sections of each stack required a drop using rope access techniques instead. One additional drop was made on the interior of each stack to collect Ultrasonic Thickness (UT) readings and photos.

FINDINGS

IA crew reviewed any pertinent documents, took photographs of observed anomalies, recorded UT readings, and examined the interior and exterior of both stacks as well as associated structural systems and appurtenances. It was concluded that both recovery boilers appeared to be mechanically functional and performing as intended, with structural integrity in fair conditions. Nonetheless, there were still different levels of degradation observed and reported for both recovery boilers.

Some stack exterior condition concerns included signs of corrosion on steel plate and rings, some broken bands, holes, exposed insulation, and failing caulk seals around penetrations. The circumferential platforms have oxidation stains present on their components and ladders, existing grating appeared to be installed improperly or insufficiently, there were potential safety hazards present, and some areas exhibited coating failure and rusting. When it comes to the stack bases and foundations, the team found that there was cracking and missing grout in the foundations of each stack, with anchor bolts showing moderate rust. The cladding of the top breeching duct connection to one of the stacks did not appear to be properly flashed, potentially allowing moisture penetration behind the cladding and insulation.

The interior inspections of the recovery boilers revealed that there were some corroded broken welds and thinning of the stack plates present that should be addressed in a timely manner. Some test ports had corrosion, rust and clogging. The crew encountered some buildup at the lower parts of the stacks and staining throughout the boiler interiors. UT readings showed some potential loss of thickness in some areas of the steel plates, but the results were still consistent for the most part.

RESULTS

Before concluding the inspection, IA advised the client to urgently address one observed issue – the welds connecting the uppermost stiffener rings to each stack were completely eroded, hanging on only by the small remaining welds at the two lifting lugs. With the client’s approval, IA performed the necessary temporary repairs to the upper stiffener rings by welding new stainless steel flat bars. This is meant to prevent further deterioration and potential falling hazards. After the work was done, IA provided the client with a list of further repair and maintenance recommendations classified based on urgency, enabling the facility to always remain one step ahead.

recovery boiler at paper mill inspection

For additional information about our company and services we provide, please give us a call anytime

770-255-1313
Call Now Button